The last 2 days have been busy with different contractors coming to view & see what minor works that need to be done....
Here's a list of work to be done in our humble home....
1. Repair of kitchen cupboard - 16 Jan 1 day
2. Repair of a toilet door frame (a little rotten @ the corner) - 16 Jan 1 day
3. Air-con whole house - 16 Jan, 1-2 days
4. Paint all walls & vanish all doors - 14 Jan According to the painter, the painting needs lots work 4 days compared to 1 day for normal 4 rm flat... which means cost us more $$
5. Polish marble floor - 19 Jan, they need 2 days for this project
6. Fix a door @ entrance of kitchen, the quote is abt $600 - $1,000!! i did not know doors are so expensive!! we are looking for alternatives like air curtains or just some blinds!!
7. Replace mirror in toilet - 16 Jan, 1 day
8. Fix fans in all rooms - 20 Jan, 1 day
9. Replace door locks - 16 Jan, 1 day
Even with the minor 'reno' work.... this shld cost us abt $8,000 - $9,000!!
Our furniture shld be coming in 23 Jan (Fri) & we target to move in on either 7 or 14 Feb, depending on the rate of our packing!!
4 comments:
looks like the reno work can be completed by 20th! and you have 2 days to clean up b4 your furniture arrives!!
WOOOO!!!
good that the contractor can start work b4 CNY :) Last time I also reno my flat (major type) in Dec and they managed to finish everything 2 weeks b4 CNY. Have to go there everyday and treat them kopi so they do a good job :D
Really busy busy huh... bought new furnitures?
Aircon---$3000
Kitchen door---$1000
Painted Wall---$1200
A place you call home---priceless!